UCF Biology Building Renovation

The Biological Sciences building requires an extensive renovation to upgrade its building systems and lab spaces, which are original to its construction in 1975. The updates will keep this heavily used facility operational to support the high volume of student and faculty traffic.

 

Start Date: July 2024
Target Completion Date: February 2026
Click to download a Project Sheet.

 

Other Key Dates
This is an estimated timeline and subject to change.
July 2024: Construction starts with electrical upgrades.
August 2024: 3rd floor finishes upgrade, brick replacement, fire alarm system replacement*
January 2025: 4th floor finishes upgrade*
May 2025: 2nd floor finishes upgrade*
August 2025: 1st floor finishes upgrade*
February 2026: Construction complete*
*projected

 

Impact to Campus (last revised July 2024): Please note the location of temporary fencing in the map below. Please avoid construction zones.

 